|
Beijing's promise to keep to the Yuan "flexible" has
brought much cheer to the world, but its impact
on the domestic power equipment market in
India would not be very significant. India's power
capacity addition targets are getting increasingly reliant
on imported power equipment and at least in the foreseeable
future, the country cannot disregard Chinese
equipment, whatever are the pecuniary consequences
of a revalued Yuan.
Statistics clearly show that Chinese main plant
equipment-boilers, turbines and generators-is a wellentrenched
phenomenon in the Indian power market.
As of today, an estimated 16,793 mw of thermal power
capacity using Chinese equipment is under construction
and expected to commission in the XI Plan period.
This represents nearly 40 per cent of the total (see
table). If one considers thermal power projects scheduled
to commission in the XII Plan period, China's role
would be much bigger.
 For several years now, domestic equipment manufacturers
were grumbling about Chinese equipment
being cheaper due to a fixed Yuan-unchanged since
2005. On an average, Chinese power equipment cost
20-30 per cent lesser than the domestic counterpart.
Several representations were made to the Centre to
impose duty on Chinese equipment with a view to
protecting domestic equipment makers. However,
experts widely believe that import Chinese equipment
will still be advantageous, even if an appreciated
Yuan makes landed costs higher. The biggest
advantage that Chinese equipment offers, more than
its competitive price, is timely delivery. Lower gestation
period means that returns on investment are
faster. The positive fiscal implications of equipment
arriving on time are huge, and could more than compensate
for higher costs.
Every leading independent power producer
appears to be relying on Chinese equipment.
Reliance ADAG Group, both as an EPC contractor and
IPP, has been sourcing BTG packages from Shanghai
Electric Corporation with whom it also entered into a
co-operation agreement. Lanco, Adani Power and
JSW Energy have a large number of projects to be
built with Chinese equipment engaging suppliers like
Harbin, Dong Fang Electric, Sepco, Sepco-III,
Sichuan Machinery, Shangdong Tiejun, etc. Out of
the 16,793 mw of thermal power capacity that is being
constructed for the XI Plan with Chinese equipment,
nearly 85 per cent is through private sector projects.
It is also noteworthy that Chinese machinery is also
being used for supercritical projects where indigenous
capabilities are still nascent.
The government has accepted the fact that power
capacity addition in the XI Plan would not be possible
without the involvement of foreign suppliers, including
Chinese. Union power minister Sushilkumar
Shinde recently said in Parliament that import duty on
power equipment for mega and ultra-mega power
projects would not be made effective up to April 2012
(the beginning of the XII Plan period), as Indian manufacturers
might not be in a position to meet the full
requirement of capacity addition in the next two
years. A committee set up by the Planning Commission
under the chairmanship of Member (Industry) had recommended, inter alia, the imposition of import
duty with a view to protecting the domestic power
equipment industry.
PFC's 'backward integration' takes off |
Power Finance Corporation's 'backward integration' plan of
financing projects relating to fuel supply for power projects
and power equipment has taken off. In late 2008, PFC
had initiated this move with a view to play a bigger and a more
supportive role in the power sector. Speaking to Electrical
Monitor, a senior official of PFC said that the lending agency
has already made disbursements, albeit in a small way, to
power equipment projects. The finer details were not immediately
available. When asked about PFC's lending to fuel
supply projects, the official said that no project was serviced
so far. According to PFC's plan, fuel supply projects could
cover a gamut of activities like development of coal blocks,
setting up of coal washeries and beneficiation plants, coal
transportation facilities and also gas-related infrastructure.
When queried about whether PFC was open to lending to
projects that sought international coal linkages, the official
replied that by far PFC would stick to domestic projects as the
other would involve an additional "country risk" apart from the
project risk. Some power producers are seen acquiring coal
properties in countries like Australia and Indonesia to ensure
fuel supplies to their upcoming power projects in India.
PFC in late 2008 had invited consultants to formulate a business
plan for the new line of activity. The company has also
formed a Facilitation Group to oversee the new business, the
official said. An industry expert said that fuel linkages and
power equipment represented critical linkages to the power
generation sector, and PFC's own backward integrated therefore
is an appropriate move. PFC's support to the power equipment
sector is a welcome move as it support's the nation's
move to create new equipment capacity to increase domestic
reliance and reduce dependence on the country's largest
equipment maker Bharat Heavy Electricals Ltd.
PFC is a significant lender to the power sector (loan sanctions
in 2008-09: Rs.57,028 crore) apart from being the
nodal agency for key projects like ultra mega power projects,
mega power transmission lines and R-APDRP |
ADVANTAGE CHINA
While the possible Yuan appreciation may give Indian
power equipment suppliers some price advantage, it
should be mentioned here that China is aggressively
encouraging power equipment exports. This encouragement,
which is so enmeshed in its national policies,
will far outweigh the rather small disadvantage that the
flexible Yuan might result in. Government support in
China comes from various forms like lower lending
rates, subsidies to export-oriented manufacturing,
favourable joint venture laws, lower costs of materials
like steel, aluminium, copper and steel, favourable
direct and indirect tax regime, etc.
On the other hand, Indian manufacturers, unmindful
of their cheaper Chinese equipment grouse, have to
pay indirect taxes (sales tax and octroi) that push up
prices by over 10 per cent. Experts therefore feel that
even if China loses, albeit partly, the "fixed" currency
advantage, Chinese equipment could still be cheaper.
THE TIME FACTOR
Some experts believe that even if Chinese equipment
were costlier than Indian equipment, domestic power
producers would not mind going for it for the sheer
delivery schedule. Currently, India's largest power
equipment maker BHEL has its order book full for at
least five years. Though the company is expanding its
manufacturing capacity, the situation is never going to
change overnight.
Consider the supercritical technology that India is
beginning to adopt very actively. India has ordered
around 50 supercritical power units out of which 28
have been bagged by Chinese companies with the
remaining by either Indian or other foreign (non-Chinese)
companies. Even the orders won by Indian
companies, mainly by BHEL, are currently mere commitments
and would need to be executed at a much
later date. BHEL is yet in the process of establishing
its capabilities in the supercritical technology area.
On the other hand, when we speak of Chinese supercritical
equipment, in most cases, the equipment has
physically arrived in India and construction work has
begun. In short, Chinese equipment currently has a
big advantage in terms of availability of technology,
shorter lead time and lower cost. These advantages
may peter out with time with the emergence of new
market forces, but in the foreseeable future, they are
too significant to be ignored.
When the power generation segment was fully in the
hands of the public sector  (Central and state government),
setting up power generation plants was a national
and social objective, but never a time-bound one. A
gestation period of 6-7 years for setting up an average-sized commercial power plant was considered normal.
Much of the gestation period was indeed the waiting
period for receiving main plant equipment from BHEL.
It may be recalled that in the X Plan Period (2002-07), the
country could barely add 20,000 mw of power generation
capacity, which was less than half of the original
target. Delayed receipt of equipment from BHEL was
allegedly the main cause of the debacle. The scenario today is radically different. When it comes to the private sector, setting up of a power
generation plant is largely, if not purely, a commercial
objective. Completing a project on time and optimizing
the project cost are topmost priorities for the
developer. In such a situation, relying on domestic
power equipment could vitiate the project's commercial
viability and at least at the moment, Chinese
power equipment appears to be first choice. New
generation power developers like Reliance Power,
Lanco, Sterlite Energy, JSW Energy and Adani
Power have endorsed this view. Together these five
developers currently have over 14,000 mw of thermal
power capacity under construction that is
scheduled to commission in the remaining part of
the XI Plan period. This does not include capacity
already commissioned or that scheduled to do so in
the XII Plan period.
Take for instance the Sasan ultra mega power project
that is being developed by Reliance Power Ltd (Anil
Ambani Group) with main plant equipment sourced
from Shanghai Electric Corporation of China. Even
though the project is envisaged to commission in the
XII Plan period, the private developer has assured that
at least one of six units will be commissioned within the
ongoing XI Plan itself. This means that the gestation
period would be compressed by at least a year and the
first unit could commission within three years from
zero date. Similar is the case with the Mundra UMPP
that is being developed by Tata Power Company.
Employment opportunities |
It has been envisaged that a generation capacity of about
78,700 mw and 1 lakh circuit km of transmission lines are
to be added in the XI Plan along with its extension and augmentation
of requisite sub-transmission and distribution
network. This would create direct employment opportunities
for 10 lakhs persons which would be required for the
construction, operation and maintenance of upcoming
power sector projects during the 11th Plan. These additional
personnel include 2 lakh engineers and supervisors, 3
lakh skilled and semi skilled workers and 5 lakh unskilled
workers & non-technical personnel. (Source: Reply to Lok
Sabha question by Bharatsinh Solanki, minister of state for
power, on March 12, 2010.)
|
Faster availability of Chinese equipment is poised to
set new benchmarks for commissioning schedules of
power plants. Whatever be the future of Chinese power
equipment in India-be it due to a stronger Yuan or any
other economic factor-India is certainly entering a new
paradigm as far as gestation periods for thermal power
plants are concerned. The gestation periods of 6-7
years seen in the government-dominated days will only
remain as an embarrassing chapter of India's power
sector history.
CASE I AND CASE II BIDDING
Several state government utilities are tying up longterm
power supplies using the tariff-based competitive
bidding guidelines. In fact, India is progressively moving
to a regime where any power purchased by state
government-owned distribution companies will necessarily
be based on tariff-based competitive bidding.
Suppliers of main plant equipment for XI Plan power projects |
(MW) |
| |
Chinese |
Other foreign |
Indian |
Grand Total |
| |
Thermal |
Hydro |
Thermal |
Hydro |
Thermal |
Hydro |
Thermal |
Hydro |
Commissioned |
4,395 |
117 |
3,331 |
3,010 |
10,485 |
354 |
18,211 |
3,481 |
Under construction* |
16,793 |
247 |
3,853 |
5,771 |
21,880 |
6,128 |
42,526 |
12,146 |
Total |
21,188 |
364 |
7,184 |
8,781 |
32,365 |
6,482 |
60,737 |
15,627 |
*Projects commissioned or under construction and expected to commission within the XI Plan period |
When it comes to Case I and Case II bidding by state
government utilities, the power purchase agreement
usually takes effect with a gap of four years (the time
given to the power producer to start supplies) and is
effective for a 25-year period. With more and more private
sector entrepreneurs turning to commercial merchant
power producers, there will be a growing need of
commissioning power plants faster. In such a scenario,
Chinese power equipment could play a very important
role-at least till comparable alternatives emerge. THE COUNTERFORCE
India is today in the midst of a power equipment revolution.
With over 15,000 mw of new power generation
capacity expected to be added every year in the medium
to long term, the power equipment represents a
huge business opportunity that cannot be overlooked.
While the traditional mainstay BHEL is in the midst of a
capacity expansion programme, there is a host of new
entrants all vying for a slice of the pie. BHEL currently
has a manufacturing capacity of 15,000 mw per year
that is being increased to 20,000 mw in the coming
years. At 20,000 mw, BHEL would appear to be technically
competent of meeting the country's requirements.
However, this is only an academic possibility. Experts
feel that BHEL, in the medium to long term, will have a
market share of around 25 per cent, implying the development
of a huge power equipment manufacturing
base in India by private and foreign companies.
Doosan equipment plant in India |
 Korea-based Doosan Heavy Industries
Ltd that is involved in several coalfired
power plants including supercritical
ones is reportedly planning to set up
a power equipment manufacturing facility
in India. According to reliable
sources, Doosan's chairman, Y.H. Park
was scheduled to visit India on June 28,
to meet government officials in this connection.
When Electrical Monitor contacted
Doosan's Mumbai office to confirm
if the visit took place, a senior company
official declined to comment on the
subject. Doosan, it is learnt, is planning
to set up the facility without any Indian
partner. It may be mentioned that 100 per
cent FDI is allowed in the power equipment
sector.
Doosan in early 2010 won a $1-billion
EPC order to set up a 1,370-mw coal-fired
power plant for the GMR Group in Raipur,
Chhattisgarh. In 2007, it landed a big
order from Tata Power to supply the boiler
package to the upcoming 5x800-mw
Mundra supercritical ultra mega power
project in Gujarat. Doosan is already
involved in NTPC's 3x660-mw Sipat
supercritical power project in Chhattisgarh,
which is amongst India's earliest
power plants using such technology.
|
Larsen & Toubro, India's leading engineering conglomerate
and an existing supplier of power equipment, has tied up with Mitsubishi Heavy of Japan to
set up manufacturing capabilities for supercritical
power equipment. JSW Group has tied up with Toshiba
of Japan to set up a manufacturing base for turbines
and generators at Chennai, Tamil Nadu. The
joint venture is aiming at an initial capacity of 3,000
mw by 2014. Bharat Forge and Alstom have come
together to form an equipment manufacturing facility
at Mundra in Gujarat. The plant is expected to go on
stream in 2013 with a capacity of 5,000 mw. Ansaldo
of Italy in which Gammon now has a controlling stake
is planning to set up a boiler manufacturing facility in
India. Besides, smaller existing players like Cethar
Vessels are upgrading their capabilities through international
collaborations. Reliance Infrastructure (Anil
Ambani Group) is also learnt to be in talks with Shanghai
Electric Corporation to set up a large power equipment
manufacturing facility in India. Besides, Central
utility NTPC has already formed a joint venture with
BHEL to produce power equipment. Thermax has tied
up with Babcock Wilson for turbines and so has
Triveni Engineering with GE.
By 2015, India will see a tremendous growth in
power equipment capacity, mainly coming from the private
sector. This will not only reduce the reliance on
BHEL but could also, depending on the price competitiveness,
be a force that Chinese suppliers would have
to contend with.
Thermal projects with Chinese equipment* |
| Promoter |
Project |
Location |
Capacity |
| (MW) |
| Central Government |
| Damodar Valley Corporation |
Raghunathpur Phase I |
WB |
1,200 |
| State Government |
|
|
|
| Haryana Power Generation Corporation |
Rajiv Gandhi TPS |
HAR |
600 |
| Tamil Nadu Electricity Board |
Mettur TPP Extension |
TN |
600 |
| Private Sector |
|
|
|
| Lanco Kondapalli |
Lanco Kondapalli |
AP |
133 |
| Adani Power |
Mundra TPP (Phase I) |
GUJ |
660 |
| Adani Power |
Mundra TPP (Phase II) |
GUJ |
1,320 |
| Adani Power |
Mundra TPP (Phase III) |
GUJ |
1,980 |
| Udupi Power Corporation |
Udupi TPP |
KAR |
1,015 |
| JSW Energy |
JSW Ratnagiri TPP |
MAH |
1,200 |
| Adani Power |
Tirora TPP |
MAH |
1,980 |
| Reliance Power |
Sasan UMPP |
MP |
660 |
| Sterlite Energy |
Sterlite TPP |
ORI |
2,400 |
| JSW Energy |
Jallipa-Kapurdi TPP |
RAJ |
945 |
| Lanco Anpara Power |
Anpara-C |
UP |
1,200 |
| Reliance Power |
Rosa TPP |
UP |
900 |
| Total |
|
|
16,793 |
*Under construction and expected to commission in XI Plan, does not include projects already commissioned in the XI Plan. |
BHEL BACK IN THE RECKONING?
Despite its growing importance, it is now being felt
that power producers, particularly those setting up
small and medium industrial power plants, are growing
wary of Chinese power equipment. While there is
no official information available on this phenomenon,
one can make some deduction on the basis of the
growing order book of BHEL from the private sector.
As discussed in Electrical Monitor, June 2010, the
PSU engineering major's performance was redeemed
to a large extent by orders for power plants from private
producers. In 2009-10, private sector orders in
the power sector amounted to 14,689 mw that was
more than thrice of that in 2008-09. In fact, private
power sector orders accounted for over 50 per cent of
BHEL's overall order inflow including that from other
sectors like industry and exports.
What will go against Chinese equipment, more
than a stronger Yuan, is lack of after-sales service.
While China is very prompt in getting plants running,
there are issues of operation and maintenance. There
are unconfirmed reports of Chinese power equipment failing, or running at sub-optimal conditions. If
China has to gain a foothold in the Indian power sector,
it would have to create a strong local service base,
if not manufacturing facilities, an analyst said. Sooner
or later, China's lack of local presence will become
its undoing.
CONCLUSION
 The next five-seven years will be a
critical phase for India's power
equipment sector with nearly
25,000 mw of capacity likely to come
on stream, largely in the private and
foreign sector. If this capacity is created
successfully and on time, it will
definitely have a bearing on the fate
of Chinese power equipment.
With time, more and more power
generation plants will be set up in private
sector, which technically opens
a big business opportunity window.
While Central and state government
agencies might desist placing orders
on Chinese equipment, the same is
not true for private sector. At least at
the moment, the tilt is clearly in
favour of China. It is also interesting
to note that Chinese equipment is
making a backdoor entry into government
projects through EPC contracts
placed on private sector  companies,
which in turn, are selecting
Chinese equipment.
How much the Yuan appreciates is only one determinant.
There are other advantages like timely delivery
that today only China can offer. When more
domestic equipment manufacturing capacity gets created,
Indian power producers will have a wider choice
and access to competitive prices. Equipment produced
locally will definitely have an advantage as
after-sales service would be
ensured. Power producers have no
fascination in particular for Chinese
equipment-it is a matter of nochoice
more than choice.
|